The federal date
Under 40 CFR 370.40 and 370.45, the inventory is due on or before March 1 every year after a facility becomes subject, and it covers chemicals present during the preceding calendar year. There is no extension provision in the federal rule. Utah's program puts it plainly: because the deadline is statutory, neither EPA nor the state can grant extensions.
| Reporting year | Due | Day of the week |
|---|---|---|
| 2025 | March 1, 2026 | Sunday: EPA says to submit before the weekend |
| 2026 | March 1, 2027 | Monday |
| 2027 | March 1, 2028 | Wednesday: first year for the new hazard categories |
When March 1 falls on a weekend
EPA's general reporting guidance says that if March 1 falls on a weekend or other non-business day, reports should be submitted before the weekend so they are postmarked or transmitted before March 1. State online systems often stay open, but a state help line will not be.
Requests outside the March cycle
If the state emergency response commission, the local emergency planning committee or the fire department asks for Tier II information, you have 30 days to provide it, and the threshold for that request is zero (40 CFR 370.10(b), 370.45(b) and 370.62). If the local committee asks for a safety data sheet you have not sent before, that is also due within 30 days (40 CFR 370.33(c)).
The software year
EPA updates Tier2 Submit every year, and only the newest version can create the current year's file. EPA's page lists Tier2 Submit 2026 for reporting year 2026, with reports due by March 1, 2027. Colorado invalidates reports made in an older version, and Utah tells facilities to use the latest version each year. See the Tier2 Submit guide.
State calendars
Every state uses March 1 for the report. Several add a filing window, a time of day, a separate fee date or a short deadline for new chemicals.
| State | What the state says | Source |
|---|---|---|
| Colorado | Report due by 5:00 p.m. MST on March 1 | CDPHE |
| Texas | Annual reports can be started in STEERS on November 1 but not submitted until January 1; file between January 1 and March 1. Initial reports within 90 days of a new chemical or new facility | TCEQ |
| Vermont | Report between January 1 and March 1 for the preceding year | Vermont EPCRA letter |
| Maryland | Report due March 1; the section 312 fee is due June 1 | MDE |
| Ohio | Report and site map due March 1; filing fee due no later than March 31 | Ohio SERC manual |
| South Dakota | Report due March 1; fee due April 1 | SD DANR |
| Pennsylvania | Form and fee by March 1; a new hazardous material at reporting quantity within 5 business days | PA L&I |
| Oregon | CHS Manager open January 1 to March 1 | Oregon State Fire Marshal |
| Utah | March 1, no extensions | Utah DEQ |
If you missed it
File as soon as you can. EPA says it has no specific process for past-due reports and has issued no formal guidance on them, but that this does not remove the obligation for earlier years. Ask your state how it wants late years filed. Our catch-up guide covers the options.
What late costs depends on how late and what was missing. At the low end, EPA's Region 4 listed a $1,500 penalty in 2024 for a single Tier II form not filed on time. States add their own charges: Kentucky a one-time $250 per facility for reports after March 1, Ohio 10% if the fee is not paid by March 31, Minnesota 100% of the fee after 60 days. At the high end, reports that leave a chemical out or go unfiled for years have settled for $28,152 (battery acid, 2025) and $138,000 (several years plus a late release notice, 2024). See Tier II penalties for every case and state late fee with its source.
- Within days: build the inventory for the missed year from that year's records, not today's fleet.
- File it complete: every chemical at or above threshold, battery acid included. A late report that leaves a chemical out counts as incomplete.
- Use the right software year or the state's own route for past years, and keep the confirmation.
- Pay the state fee and any late fee the state assesses, then put next year's records request on the calendar for December.
Common questions
Can I get an extension?
The federal rule has no extension provision, and Utah states that neither EPA nor the state can grant one because the deadline is statutory. Plan to file before March 1.
When is the first report due for a new site?
March 1 of the year after the site first held a chemical over its threshold. The section 311 SDS submission is due within three months. See new facilities.
Is the fee due on the same day?
Usually, but not everywhere. Maryland takes the fee by June 1, Ohio by March 31 and South Dakota by April 1.
We build the battery and chemical inventory, check every threshold and file in your state's system. $950 a site per year, $750 a site from the third site. State fees extra.
Get a quote- 40 CFR 370.40, March 1 inventory
- 40 CFR 370.45, timing
- 40 CFR 370.33, SDS timing
- 40 CFR 370.62, information requests
- EPA, general reporting guidance (weekend rule, past-due reports)
- EPA, Tier2 Submit software
- EPA, EPCRA hazard category revisions
- Colorado CDPHE, Tier II reporting
- TCEQ, Tier II reports and timelines
- Vermont Emergency Management, EPCRA cover letter
- Maryland MDE, Community Right-to-Know Fund
- Ohio SERC manual
- South Dakota DANR, fee reporting guidance
- Pennsylvania L&I, Tier II and PATTS
- Oregon State Fire Marshal, CHS Manager
- Utah DEQ, Tier 2 chemical inventory
- EPA Region 4, EPA Fines Companies for Alleged Violations of EPCRA, September 30, 2024
- EPA Region 3, Allen Distribution consent agreement, EPCRA-03-2025-0070
- EPA Region 5, Sherwood Food Distributors consent agreement, EPCRA-05-2024-0024
- EPA, State Tier II Reporting Requirements and Procedures: Kentucky (late fee under KRS 39E.990(2))
- Minnesota Rules chapter 7507
- Ohio Administrative Code 3750-50-01